Hi expperts,
I set deadline monitoring and the definition is :
5 days after Work Item Creation
I want to define the time ( 5 days ) not hardcoded but using expression or container element or something like this.
Is it possible?
One more question.
in order to test the deadline monitoring, I defined 5 minutes instead of 5 days temporary for tests only in DEV environment.
Now I want to test it in QA environment and I need to do the tests in QA according to 5 minutes in order not to wait for days.
So after tests completion I need to transfer CR and replace minutes ->> days.
Does anybody have another solution for this issue?
Thanks,
Nina